Line 1: | Line 1: | ||
====== Project periodization ====== | ====== Project periodization ====== | ||
- | If the cell " | + | If the cell " |
The purchase and sales invoice rows described above appear in the project periodization report. | The purchase and sales invoice rows described above appear in the project periodization report. | ||
Line 10: | Line 10: | ||
- | ===== 1. Filters and filter options ===== | + | ===== 1.1. Fine-tuning ===== |
+ | |||
+ | Can be selected in fine tuning : | ||
+ | |||
+ | {{: | ||
+ | |||
+ | * **Leaves zero row to the document** - | ||
+ | * if the option is active the account, object or project can also be changed later on the purchase invoice | ||
+ | * if the option is not active, can only select the time period for periodization | ||
+ | ===== 1.2. Filters and filter options ===== | ||
* **Project** - filtered by row project | * **Project** - filtered by row project | ||
Line 38: | Line 47: | ||
* **WIP balance** - shows the balance of the project selected to the invoice row | * **WIP balance** - shows the balance of the project selected to the invoice row | ||
* **Qty to cost** - quantity that is expensed for the given period | * **Qty to cost** - quantity that is expensed for the given period | ||
- | * **% to Income** - %, which is charged as an expense | + | * **% to Income** - %, that is expensed |
* **Amount to cost** - the amount that is expensed for the given period | * **Amount to cost** - the amount that is expensed for the given period | ||
* **Start** - periodization beginning, transaction periodization date | * **Start** - periodization beginning, transaction periodization date | ||
Line 51: | Line 60: | ||
* The purchase and sales invoice must be created with a check mark in **" | * The purchase and sales invoice must be created with a check mark in **" | ||
* You can **periodize by quantity, % or amount** in the project periodization report | * You can **periodize by quantity, % or amount** in the project periodization report | ||
- | * **Quantity** - the % and amount corresponding to the quantity | + | * **Quantity** - the % and amount |
* **%** - sum is calculated by % (quantity is not calculated) | * **%** - sum is calculated by % (quantity is not calculated) | ||
* **Sum** - % is calculated by the sum (quantity is not calculated) | * **Sum** - % is calculated by the sum (quantity is not calculated) | ||
Line 99: | Line 108: | ||
=== 3.1.2. Purchase invoice periodization by changing the project and object === | === 3.1.2. Purchase invoice periodization by changing the project and object === | ||
+ | |||
+ | If you want to change the original project, object or account during project periodization, | ||
+ | |||
+ | {{: | ||
+ | |||
+ | Example of project periodization: | ||
{{: | {{: | ||
Line 112: | Line 127: | ||
=== 3.1.3. Purchase invoice periodization by changing the project, object and account === | === 3.1.3. Purchase invoice periodization by changing the project, object and account === | ||
+ | |||
+ | If you want to change the original project, object or account during project periodization, | ||
+ | |||
+ | {{: | ||
+ | |||
+ | Example of project periodization: | ||
{{: | {{: | ||
Line 119: | Line 140: | ||
{{: | {{: | ||
- | The cost is periodized | + | The cost is periodized from the original corresponding |
{{: | {{: |